Project TOCOMA 400 kV Electrical Substation
Description Scope of work: EPC
Location Ciudad Guayana (Venezuela)
Client CORPOELEC
Finish date 2015
More info about the project
Transport substation, composed of 7 bays set out in a one-and-a-half breaker arrangement for a working voltage of 430 kV and a transport capacity of 2.5 GW. This substation works as both a transport and collector substation since it collects the rated power generated by the TOCOMA dam, composed of ten 216 MW generators.
Tocoma Substation | Venezuela
This substation works as both a transport and collector substation since it collects the rated power generated by the TOCOMA dam, composed of ten 216 MW generators.