TL 138 kV BABAHOYO – MILAGRO
BABAHOYO - MILAGRO Substations (Ecuador)
Project Transmission Line 138 kV BABAHOYO - MILAGRO Substations
Description Scope of work: EPC
Location Ecuador
Client CELEC
Finish date 2019
New Electrical Transmission System
More than 700 thousand inhabitants of the province of Ríos will benefit from the recently inaugurated power transmission system, which consists of a 42 km Transmission Line and the expansion of the Milagro and Babahoyo substations.
Related Content
News
CELEC awards new substation to TSK in Ecuador
CELEC EP awards TSK the execution of a transmission line and the expansion of two electrical substations belonging to the Ecuadorian National Transmis[...]Projects