SALAS 132/400 kV Substation

Salas (Spain)

Project SALAS 132/400 kV Substation

Description Scope of work: EPC

Location Salas, Asturias (Spain)

Client Saltos del Navia

Finish date 2010

More info about the project

132/400 kV booster substation.
Installed rated power of 300 MW.
Wind farm collector substation, with a rated power of 300 MWA, boosting capacity of 132kV/400 kV, composed of a bank of four single-phase autotransformers, three in operation and one as backup, transferring both 400 kV and 132 kV by means of a pilot bar. The project uses single-phase benches to ensure the installation is flexible; if one of the banks doesn’t work the transfer is performed with the pilot bar at both 400 kV and 132 kV, which means that the plant’s downtime is minimal

Related Content

Project

SALAS 400 kV Substation Enlargement

Scope of Work: Enlargement

More info

Projects

Throughout these years we have carried out numerous projects in this activity

More Projects